🏭 Soil stabilization in an industrial area without interrupting operations.
- caio3421
- Mar 30
- 1 min read
📌 Project details:
Issue: Soil settlement of up to 21 cm
Cause: Rainwater infiltration due to a leaking pipeline
Solution: Injection of high-strength two-component expanding polyurethane
Execution time: 2 days
The project was carried out at a motor factory in Jaraguá do Sul (SC), completed in just 2 days with no need to interrupt industrial operations.
The area had low load-bearing capacity and the presence of voids in the subsoil, resulting in settlement of the concrete slabs in the export yard and engine storage area.
⚠️ With the application of our technology, it was possible to:
✔ Precisely level the ground
✔ Fill subsoil voids
✔ Restore the soil’s load-bearing capacity
The result was a fast, non-invasive, and highly efficient solution, ensuring structural safety and operational continuity.
📩 Contact us to request a technical assessment for your project.